| Project
work started |
Unit I
Commissioned |
Unit II Commissioned |
Size of the unit |
Manpower employed |
Skilled |
|
100 acres |
982 |
57 |
330 |
595 |
26 nos |
Highlights of the Project
 |
Completed in a record 22 months & at a cost of around Rs.65
crore (Rs.650 million), against the estimated time of 40 months & cost of
Rs.75crore (750 million). |
 |
Early & efficient completion possible because of project re-designing by
RSWI, Canada. |
 |
Optimal scheduling and project monitoring by the Group. |
 |
Low on capital cost & efficient in generation (High PLF). |
Technical Highlight
 |
Dam toe and Irrigation canal based project. |
 |
Catchment area spread over approximately 6,000 sq. km. |
 |
Full Reservoir Level (FRL) is 355.4 m. |
 |
Wide head range of 7-21 m and discharge varying from 25-54 cumecs. |
 |
Two turbo generators with 6.75 MW rated capacity installed; each unit designed
for 20% continuous overload. |
Machinery / Equipment
 |
Vertical shaft Kaplan Turbine and its auxiliaries. |
 |
11 KV semi umbrella synchronous generator and auxiliaries. |
 |
9MVA 11/33 KV generator transformers. |
 |
33 KV vacuum circuit breakers. |
 |
1 MVA 33 KV/415 V auxiliary transformer. |
 |
Fire protection system. |
 |
50/10 Ton capacity EOT crane. |
 |
110 V DC with battery back up. |
 |
AC distribution. |
 |
PLCC system. |
|